Overnight restrictions are needed to prepare for the shift and other work
By the end of this week, traffic is expected shift to new roadway on a portion of I-70, marking another project milestone. Traffic on a three-mile section of eastbound I-70 from S.R. 227 to the Ohio state line will move to new pavement toward the median.
The shift will happen in two phases with drivers in the left lane expected to be on the new pavement on or after early Wednesday, Oct. 21. The right lane will shift to the new roadway by early Friday, Oct. 23. Traffic will stay in this configuration through spring. This will allow crews to move their work zone to the outside lanes.
Overnight restrictions are planned Tuesday and Thursday to prepare for shift. Additional overnight restrictions are needed for bridge work and other improvements in the western portion of the project corridor.
Overnight Closures This Week
Monday, Oct. 19 – Wednesday, Oct. 21
- Eastbound I-70 ramps to and from S.R. 1 closed
- Eastbound I-70 reduced to one lane from Brick Church Road to Centerville Road
Tuesday, Oct. 20
- Eastbound I-70 reduced to one lane from west of U.S. 35 to the Ohio state line
Thursday, Oct. 22
- Eastbound I-70 ramps to and from U.S. 40 closed
- Eastbound I-70 ramps to and from S.R. 227 closed
- Eastbound I-70 reduced to one lane from west of U.S. 35 to the Ohio state line
Friday, Oct. 23 (10 p.m. Friday to 10 a.m. Saturday)
- Eastbound I-70 ramps to and from S.R. 1 closed
- Eastbound I-70 reduced to one lane from Brick Church Road to Centerville Road
- Westbound I-70 ramps to and from S.R. 1 closed
- Westbound I-70 reduced to one lane near S.R. 1
Overnight closures are 8 p.m. to 7 a.m. unless otherwise noted.
Construction Speed Limit
The construction zone speed limit remains active on I-70. A reduced speed of 55 mph is in place for the duration of Revive I-70 work. It is important for drivers to slow down and avoid distractions in work zones.