Lane restriction this weekend on eastbound I-70

Temporary ramp closures to begin next week

Lane restrictions are scheduled this weekend on eastbound I-70 to prepare for the start of construction early next year. Significant delays are expected, and drivers are strongly encouraged to plan ahead and use alternate routes when possible. The work is expected to be completed over the next two weekends.

Friday, Oct. 24 – Monday, Oct. 27 (10 p.m. Friday – 7 a.m. Monday)

  • Eastbound I-70 reduced to a single lane from State Road 1 to Centerville Road

Friday, Oct. 31 – Monday, Nov. 3 (10 p.m. Friday – 7 a.m. Monday)

  • Eastbound I-70 reduced to a single lane from Brick Church Road to Jacksonburg Road

Temporary Ramp Closures

The ramps from eastbound and westbound U.S. 40 to eastbound I-70 and eastbound I-70 to eastbound U.S. 40 are expected to close on or after Tuesday, Oct. 28. The closures are expected to last through late 2025. The signed detour utilizes U.S. 27.

The temporary ramp closures will allow crews to continue improvements at the U.S. 40 interchange. The partial cloverleaf is being replaced with a diamond interchange with single-lane roundabouts, and the existing loop ramps are being removed. The interchange is expected to open in final configuration in 2027. 

Lane Closures Next Week

Drivers can expect the following restrictions next week:

Monday, Oct. 27 (8 p.m. Monday – 7 a.m. Tuesday)

  • Ramps from eastbound and westbound I-70 to westbound U.S. 40 closed
  • Eastbound I-70 reduced to one lane near U.S. 35

Monday, Oct. 27 – Thursday, Oct. 30 (8 p.m. – 7 a.m. each night)

  • Westbound I-70 reduced to one lane from Brick Church Road to Jacksonburg Road

Tuesday, Oct. 28 – Friday, Oct. 31 (8 p.m. – 7 a.m. weeknights and 8 p.m. Friday to 10 a.m. Saturday)

  • Westbound I-70 reduced to one lane from the Ohio state line to U.S. 40

All work is weather-dependent, and schedules are subject to change.

Temporary Closure at Washington Road Rescheduled for Early 2026

The temporary closure of the Washington Road overpass bridge won’t begin until early 2026. The closure from west of Kepler Road to Moyer Road had been scheduled to start in early November.

Construction Speed Limit
The construction zone speed limit remains active on I-70. A reduced speed of 55 mph is in place for the duration of Revive I-70 work. It is important for drivers to slow down and avoid distractions in work zones.