Traffic to shift to new roadway on eastbound I-70
As progress continues on the I-70 corridor, two temporary ramp closures are scheduled to begin next week, and traffic on a section of eastbound I-70 will shift to new roadway, marking another project milestone.
Two Temporary Ramp Closures
Two ramps will close temporarily to accommodate additional improvements in the area. The exit ramp from eastbound I-70 to S.R. 227 and the entrance ramp from U.S. 40 to eastbound I-70 are expected to close in mid-October. Both ramps are expected to reopen in December. Signed detours will be in place.
To access S.R. 227 from eastbound I-70, take U.S. 40 to S.R. 227. To access eastbound I-70 from U.S. 40, take westbound I-70 to S.R. 227 to eastbound I-70.

Traffic Shift
Traffic on a portion of eastbound I-70 is shifting to new roadway, marking another project milestone. Traffic on eastbound I-70 from S.R. 227 to the Ohio state line will shift to new pavement toward the median for this three-mile stretch of the interstate on or after Monday, October 12. Traffic will stay in this configuration through the spring. This will allow crews to move their work zone to the outside of the interstate.
Overnight Restrictions This Week
Friday, October 9 (10 p.m. Friday to 10 a.m. Saturday)
- Eastbound I-70 reduced to one lane from Brick Church Road to Centerville Road
- Ramps to and from S.R. 1 and eastbound I-70 closed
Construction Speed Limit
The construction zone speed limit remains active on I-70. A reduced speed of 55 mph is in place for the duration of Revive I-70 work. It is important for drivers to slow down and avoid distractions in work zones.