Revive Report – August 2026

It’s the second year of construction and significant progress has been made along the I-70 corridor. From west of U.S. 35 to the Ohio state line, capacity is being added, pavement is being replaced, and bridges improved. When complete, I-70 will be six lanes (three in each direction) along this area of the corridor. Improvements are also underway at the U.S. 35 and U.S. 40 interchanges.

The U.S. 27 ramps to and from eastbound I-70 reopened in late July. These ramps were closed in April for rehabilitation, which included extensive work to patch the concrete, connect the ramps to I-70, and improve acceleration and deceleration lanes. The S.R. 1 ramps to and from eastbound I-70 recently reopened. They closed in late May to be rehabilitated and reconstructed. Drainage work and resurfacing were also completed.

Pavement rehabilitation and bridge improvements are underway from west of S.R. 1 to west of Centerville. The Washington Road bridge reopened to traffic in late July. It was closed to rehabilitate the bridge’s surface and structure.

There are several upcoming changes to traffic patterns along the I-70 corridor in the next few months. Make sure to pay attention to posted signage.

Significant changes are underway to improve safety and mobility at the U.S. 35 and U.S. 40 interchanges.

Improvements include removing the loop ramps, constructing roundabouts, and eliminating weaving movements from the entrance and exit ramps.

Roundabouts have been in use for decades and are a safer alternative to traffic signals and stop signs. They improve traffic flow, reduce speeds, and lower the number of conflict points where crashes can happen. They are also designed to handle large vehicles such as trucks and buses.

U.S. 35 Interchange

  • Traffic is expected to shift in late August.
  • Northbound and southbound traffic will use both roundabouts.
  • New ramps are being built to tie-in to the roundabouts.
  • The interchange is expected to open in final configuration in late 2027.
U.S. 35 Interchange | July 2026

U.S. 40 Interchange

  • The western roundabout is about 60% complete.
  • Work on the eastern roundabout is underway.
  • New ramps are being built to tie-in to the roundabouts.
  • The interchange is expected to open in final configuration in late 2027.
U.S. 40 Interchange | July 2026

Have you seen these signs along the Revive I-70 corridor? They show truck drivers which lane to be in as they move through construction zones. This helps to increase the longevity of temporary pavement in place and to reduce the impact of heavy loads, especially on reduced shoulders on bridges. Drivers should slow down in construction zones, and trucks need to use designated lanes.

Read More Traffic & News Updates