Update: Temporary closure of single U.S. 40 ramp scheduled for week of July 21

Overnight restrictions to accommodate work on the corridor this week

The Revive I-70 project team has updated the construction schedule to begin work on improvements at the I-70 and U.S. 40 interchange near Richmond. The ramp from westbound I-70 to westbound U.S. 40 is expected to close the week of July 21 and reopen in mid-September. During the closure, crews will remove existing pavement and begin construction at the interchange. A closure date and detour information will be shared this week.

Short-term restrictions will be needed this year for the eastbound I-70 ramp to westbound U.S. 40, but the temporary, 60-day closure is not expected until 2026.

Lane Restrictions This Week
Drivers can expect the following traffic impacts this week for Revive I-70 construction:

Monday, July 14 and Tuesday, July 15

  • Overnight lane closure on westbound I-70 from Ohio state line to S.R. 227

Wednesday, July 16 through Friday, July 18

  • Overnight lane closure on eastbound I-70 from S.R. 121 to Ohio state line

Thursday, July 17

  • Overnight lane closure on westbound I-70 from U.S. 27 to Union Pike
  • Union Pike will be closed from 9 p.m. Thursday and reopen by 6 a.m. Friday to set beams on the I-70 overpass bridge at Union Pike.
  • Overnight lane closure on westbound I-70 from Centerville Road to Mineral Springs Road for pavement patching.

Friday, July 18

  • Overnight lane closure on westbound I-70 from Centerville Road to Washington Road from 10 p.m. Friday until 10 a.m. Saturday for pavement patching.

Unless otherwise noted, overnight closures are 8 p.m. to 7 a.m. each night. Work is weather-dependent, and schedules are subject to change.

Construction Speed Limit
The construction zone speed limit remains active on I-70. A reduced speed of 55 mph is in place for the duration of Revive I-70 work. It is important for drivers to slow down and avoid distractions in work zones.