As progress continues on the Revive I-70 corridor, overnight restrictions will be needed Friday and next week.
Friday, August 28 (10 p.m. Friday – 10 a.m. Saturday)
- Eastbound I-70 reduced to one lane from Brick Church Road to Centerville Road
- Westbound I-70 reduced to one lane at the Whitewater River Bridge
Monday, August 31
- Ramps on eastbound I-70 to and from S.R. 1
- Eastbound I-70 reduced to one lane from Brick Church Road to Centerville Road to set barrier wall
- Westbound I-70 reduced to one lane for guard rail repair near Jacksonburg Road
Thursday, September 3
- Eastbound I-70 reduced to one lane from S.R. 227 to Smyrna Road
All closures are 8 p.m. to 7 a.m. daily unless otherwise noted.
Construction Speed Limit
The construction zone speed limit remains active on I-70. A reduced speed of 55 mph is in place for the duration of Revive I-70 work. It is important for drivers to slow down and avoid distractions in work zones.