Weekend lane restrictions postponed on eastbound I-70

Work is rescheduled for next weekend

Due to rain in the forecast, planned weekend lane restrictions will be postponed to next weekend. Other restrictions are planned for tonight and next week, and temporary ramp closures are expected later this month as work progresses.

Lane Closures This Week
Drivers can expect the following restrictions this week:

  • Friday, Oct. 17 (8 p.m. Friday to 10 a.m. Saturday)
  • Westbound I-70 reduced to one lane from Centerville Road to State Road 1
  • Westbound I-70 reduced to one lane from near the East Fork Whitewater River bridge to New Paris Pike

Lane Closures Next Week
Drivers can expect the following restrictions next week:

Monday, Oct. 20 (8 p.m. Monday – 7 a.m. Tuesday)

  • Westbound I-70 reduced to one lane from Centerville Road to Brick Church Road

Monday, Oct. 20 – Wednesday, Oct. 22 (8 p.m. to 7 a.m. each night)

  • Westbound I-70 reduced to one lane from New Paris Pike to near the East Fork Whitewater River bridge

Tuesday, Oct. 21 (8 p.m. Tuesday – 7 a.m. Wednesday)

  • Westbound I-70 reduced to a single lane from Centerville Road to Jacksonburg Road

All work is weather-dependent, and schedules are subject to change.

Upcoming Weekend Closures
Weekend lane restrictions are scheduled to resume next week to allow crews to widen eastbound I-70 to prepare for construction next year.

Friday, Oct. 24 – Monday, Oct. 27 (10 p.m. Friday – 7 a.m. Monday)

  • Eastbound I-70 reduced to a single lane from State Road 1 to Plum Creek

Friday, Oct. 31 – Monday, Nov. 3 (10 p.m. Friday – 7 a.m. Monday)

  • Eastbound I-70 reduced to a single lane from S.R. 1 to Greens Fork

Significant back-ups and delays were seen with similar restrictions this month. Drivers are strongly encouraged to plan ahead and use alternate routes when possible.

Temporary Ramp Closures
Temporary ramp closures are scheduled for later this month. The ramps from eastbound and westbound U.S. 40 to eastbound I-70 and eastbound I-70 to eastbound U.S. 40 are expected to close on or after Monday, Oct. 27. The closures are expected to last through late 2025 and will allow crews to continue improvements at the U.S. interchange. The signed detour utilizes U.S. 27.

The partial cloverleaf at the U.S. 40 interchange is being replaced with a diamond interchange with single-lane roundabouts. The existing loop ramps are being removed. Similar improvements are being made at the U.S. 35 interchange. Both interchanges are expected to be open in final configuration in 2027.

Temporary Closure at Washington Road to Begin in November
The Washington Road overpass bridge is expected to close on or after Monday. Nov. 3. Washington Road will be closed from west of Kepler Road to Moyer Road. The closure is expected to last through spring 2026. A signed detour will be in place.

Construction Speed Limit
The construction zone speed limit remains active on I-70. A reduced speed of 55 mph is in place
for the duration of Revive I-70 work. It is important for drivers to slow down and avoid distractions